|
Wind home Index |
|
|
This page discusses matters that relate to wind-generated
electricity, especially as it is developing in South Australia.
It is intended to be factual; any opinion or speculation is clearly shown
as such.
I would appreciate being informed of any errors that I might have made (email
address above).
The Australian Energy Market Operator's (AEMO) 2011 SA Supply and Demand Outlook report stated that wind generation now supplies approximately 20% of electricity demand (about 3000 GWh of the total of approximately 14 500 GWh consumed in a year). It also showed that SA's greenhouse emissions from electricity generation had decreased from about 10 000 000 tonnes in 2005/06 to about 8 000 000 tonnes in 2010/11. In late 2010 more than half of Australia's installed wind power was in South Australia. Before 2003 there was only one large wind turbine in South Australia: a 150kW unit at Coober Pedy. As of December 2010 there was 1150MW of operational wind farm capacity in South Australia and the state had a higher installed capacity of wind power per capita than any nation in the world (see Installed wind power per capita and How does Australia compare?).
| ||||||||||||||||||||||||||
|
Wind home Top SA wind farms Index |
|
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Actual productivity as a percentage of installed capacity (Capacity factor) is about 35% for wind power and 20% for solar power in Australia, so power generated by these solar systems would be about one seventieth of wind power.
|
Operating SA wind farms, Megawatts installed capacity At December 2011 |
|---|
|
|
Wind home Top SA wind farms Index |
|
The graph at the right shows average generation data extracted from AEMO records for SA wind farms. Generation data for all Australian farms handled by the AEMO can be seen on my Wind Power Australia page and an explanation of how the data were obtained is given there.
A wind turbine rarely generates at 100% of its installed capacity.
The percentage of the
installed capacity that is actually achieved is called
the capacity factor.
The installed capacities of these wind farms is given
above.
|
Power consumption in Australia as a whole is also increasing.
|
South Australia is of course connected to the SE Australian power grid which supplies large parts of NSW, Queensland, Tasmania and Victoria with electricity. SA imported less power, and exported more power, to the other states over this period (see the graph below).
The magnitude of the increase in power demand in Australia over this period has made the closing down of the old and polluting, coal burning, Thomas Playford Power Station at Port Augusta impossible, under the circumstances.
The orange columns are coal-fired power; yellow, gas-fired; blue, wind;
and black is power imported from the eastern states by the interconnectors.
The red line is total annual energy.
|
The report stated that "This corresponds with recent increases in wind
generation in South Australia, and may have been influenced by drought
conditions affecting supply in the eastern states."
|
|
|
|
Wind home Top SA wind farms Index |
|
The AEMO SA Supply and Demand Outlook, 2011 stated that "The maximum demand for the year was 3 433 MW, and occurred 4:30 PM (Australian Eastern Standard Time) Monday 31 January 2011 (at a temperature of 42.9°C)." and "Wind contributed only 60 MW during the summer 2011 maximum demand... However, at times during the week either side of the maximum demand, that output reached 873 MW."
Wind farm generation at times of peak demand tends to be low. Peak demand relies heavily on gas-fired generators.
Summer peak demand days generally coincides with high generation from
solar
power systems, as skies are usually clear at the time.
However, as
the actual peak usually comes late in the day – when people are
coming home from work, turning air conditioners on and preparing dinner
– it coincides with declining solar PV generation.
|
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
The journal Windpower Monthly (July 2003) stated that the average electricity load in SA is 1500 MW. Minimum overnight demand is about 1000 MW (pers. com. Lewis W. Owens, then Chairman of Essential Services Commission of SA).
|
Wind home Top SA wind farms Index |
Growth of the SA wind industry
Unfortunately by March 2011 there was a downturn in wind farm construction. At that time there was only one small wind farm (Bluff Range, 25 turbines) under construction in SA, and there were no others ready to begin construction.
Over the past decade worldwide wind energy generation capacity has been
increasing by around 25% per year while wind energy prices have been falling
by 4% per year.
If the SA government was serious about maximising SA's sustainable power it could spend taxpayer's money much more productively than on tiny 'showcase' projects, for example by upgrading power transmission lines. | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Wind home Top SA wind farms Index |
|
Climate change
is happening and must be minimised;
Australia and the world must move away from fossil fuels.
I don't think that any reasonable and informed person can doubt this any
more.
Unfortunately Australian governments are not giving climate
change the high priority that it needs.
Certainly wind power is not 'the answer' to climate change. Only a naive person would believe that there is a single answer, and only a naive person would object to wind power because it is not 'the answer'. It is a part of 'the answer'. Other parts are energy conservation, technological innovation, development of other forms of sustainable energy, and education. (I have listed some suggestions in What should be done.)
One of the greatest problems for future development of wind power in South Australia is the lack of transmission lines in many of the areas with good wind resources. No further development is possible on the Eyre and Yorke Peninsulas for lack of transmission capacity, and the huge potential resource on Kangaroo Island cannot be developed for the same reason. I would hope and expect that national parks and conservation parks would be kept free of wind farm developments. Will we get sick of the sight of wind turbines? Quite possibly. The alternatives, it seems to me, are either to throw caution (and sanity) to the wind and continue with fossil fuels, or to totally change our life-styles and enormously cut down on the amount of energy that we use, in our personal lives and in industry. I cannot imagine our society being ready or willing to do the latter and I hope we will not be so stupidly short-sighted as to do the former. |
|
Wind farms in SA
| |
|
Allendale (south east SA) Ardrossan (Yorke Pen.) Barn Hill (Red Hill) Bluff Range (Hallett #5) Brown Hill Range (Hallett #1) Canunda (Millicent) Carmodys Hill (Gulnare/Jamestown) Cathedral Rocks (Port Lincoln) Ceres Project (Yorke Pen.) Clements Gap (Crystal Brook) Collaby Hill (Crystal Brook) Coober Pedy (far north) Crystal Brook Exmoor (South East) Eyre Peninsula wind project Green Point (South East) Hallett Hill (Hallett #2) Hallett wind farms Hornsdale (Jamestown) Keyneton (Lower North) Lake Bonney wind farms (Millicent) |
Lake Bonney Stage 1
(Millicent) Lake Bonney Stage 2 (Millicent) Lake Bonney Stage 3 (Millicent) Mount Bryan (Hallett #3) Mount Millar (Cowell/Cleve) Myponga-Sellicks Hill (Fleurieu) North Brown Hill (Hallett #4) Port Augusta/Lincoln Gap Robe (Millicent) Robertstown (Clare) Snowtown (Clare) Snowtown, Stage 2 Starfish Hill (Fleurieu Pen.) Stony Gap (Clare) Troubridge Point (Yorke Pen.) Vincent North (Yorke Pen.) Waterloo (Clare) Wattle Point (Edithburgh) Willogoleche Hill (Hallett) Woakwine Range (Millicent) Worlds End (Burra) |
|
Wind farms by region Other proposed SA wind farms | |
|
Note: Latitudes and Longitudes are given below in decimal degrees.
They are given to two decimal places because this defines the location
to ±1 km; a wind farm is a large thing and typically covers a
number of kilometres.
Note that the wind farms listed here as proposed or approved will not necessarily ever be built. You can't be sure that anything is going to be built until it starts happening. |
|
All operating wind farms and those under construction are shown here. The 'MW' column shows installed capacities. Also see Power generation of wind farms.
|
| Colour coding for wind farm status, below |
|---|
| Proposed |
| Approved |
| Under construction |
| Operating |
| Wind generation in SA by region |
|---|
|
| Average generation up to the end of December 2011 in MW. The averages were calculated from differing starting dates for the various wind farms. Mid North wind farms were responsible for 59% of the total. |
|
Wind home Index Top |
|
|
Climate change will result in the
extinction of thousands or even millions of species.
It will cause the displacement of billions of people, and quite possibly the
deaths of billions as well – from flooding of fertile river deltas,
coasts, and desertification of large areas of what is now farm land, and
from the mass migrations and wars that will result.
Ocean acidification, also caused by the release of huge amounts of carbon
dioxide into the atmosphere, is another looming disaster.
Australia ranks 53rd in the world in population, but sixth in the world in the CO2 produced by its electricity industry. Australia has 0.3% of the world's population, but produces 1.5% of the world's CO2. We Australian's have an ethical responsibility to lift our game. Changing from fossil-fuel generated electricity to sustainably generated electricity is one way we can do that. In early 2003 SA had negligible sustainably generated electricity, just nine years later, more than 20% of our electricity is generated from the wind. That is remarkable progress. In 2011 both Denmark, the world's leading nation, and SA had around 700 Watts of installed wind power per person. I live in Mid North SA where we have around 30 000 Watts per person (see graph above)! If the rest of South Australia, Australia, and the world was to follow our lead we would be well and truly on top of the climate change problem. We are well up among the world leaders in renewable energy. This is something of which those of us in the Mid-North, who either work in or support the wind industry, should be intensely proud. It is also progress that is in danger of ending if the Liberals should get into government in SA. |
|
|
Below is a conceptual map of SA.
The numbers in each cell are the Latitude and
Longitude, the main town in each area is shown in the cells.
Placing the mouse over the highlighted bits will show which wind farms are
in that area, clicking will allow you to get to the details
of those wind farms.
Similar sections are in the pages on
NSW and
Victoria and
WA.
This section can be used as an alternative to the Wind farm by region section. |
| 26,133 –
far north, not to scale Coober Pedy, Leigh Creek, Marla, Woomera | |||||||
| 32,133 Ceduna | 32,134 Wirrulla | 32,135 Minnipa | 32,136 | 32,137 Pt Augusta | 32,138 Orroroo | 32,139 Yunta | 32,140 Olary |
| 33,134 Elliston | 33,135 Wudinna | 33,136 Cowell | 33,137 Whyalla | 33,138 Clare | 33,139 Robertstown | 33,140 Canopus | |
| 34,135 Pt Lincoln | 34,137 Minlaton | 34,138 Adelaide | 34,139 Swan Reach | 34,140 Renmark | |||
| 35,137 Kingscote | 35,138 Cape Jervis | 35,139 Meningie | 35,140 Lameroo | ||||
| 36,139 Kingston | 36,140 Bordertown | ||||||
| 37,139 Robe | 37,140 Mt Gambier | ||||||
| 38,140 Pt Macdonnell | |||||||
|
The status of the wind farms below is correct, so far as I know, in April
2011.
Lat 26 to 31, Long 129 to 140 – Far north
Lat 32, Long 137 – Port Augusta
Lat 33, Long 136 – Cleve/Cowell
Lat 33, Long 138 – Clare
Lat 33, Long 139 – Robertstown
Lat 34, Long 135 – Port Lincoln
Lat 34, Long 137 – Ceres Project
Lat 35, Long 137 – Kingscote/Edithburgh
Lat 35, Long 138 – Cape Jervis
Lat 37, Long 139 – Robe
Lat 37, Long 140 – Mount Gambier
Lat 38, Long 140 – Port Macdonnell |
|
Wind home Top SA wind farms Index |
|
Acciona have a page from which newsletters on all their Australian wind farms can be downloaded: "http://www.acciona.com.au/community/ newslettersAndUpcomingEvents/index.php" (no spaces in URL). Acciona's Community Relations Coordinator for this wind farm is Genevieve Bowyer, free call 1800 283 550 or email to info@allendalewindfarm.com.au. The District Council of Grant granted approval to Acciona's Development Application in March 2010; however this was appealed; see 'Court case', below. It is proposed that the wind farm be about two kilometres east of Allendale East and about 18 km south of Mount Gambier. Port Macdonnell is about seven kilometres SW of the farm. Acciona arranged a visit about September 2010 to the Waubra Wind Farm for the local people who are expecting to become a part of the Allendale project. As well as a guided tour of the wind farm the Allendale people had a chance to chat to farmers involved in the Waubra Wind Farm. Court caseA dairy farmer, Richard Paltridge, has brought a case against this wind farm in the Environment Resources and Development (ERD) Court. Adelaide Now (2011/01/29) stated that Mr Paltridge "has concerns relating to the humming noise of the turbines and its possible long-term health impact, the flashing lights on turbine towers and obstruction of views".Richard Paltridge's appeal was upheald and Justice Costello, while rejecting evidence pertaining to health problems, upheld the appeal on the basis of visual amenity. (Reported in The Courier 2011/06/24.) It seems that this is the first time an appeal against a wind farm has been upheald on visual amenity grounds. On 2011/07/11 ABC on-line news carried an article stating that Acciona is appealing against the ERD Court's ruling. Community fundingAcciona have not responded to my inquiry regarding community funding at Waubra; perhaps, unlike a number of other companies, they don't provide any?
|
| Further information on Allendale wind farm | |
|---|---|
| Tower height | Up to 80m |
| Blade length | Up to 41m |
| Maximum height – to blade tip | Up to 121m |
| Expected greenhouse CO2 abatement | 180 000 tonnes per year |
|
Wind home Top SA wind farms Index |
Barn Hill Wind Farm (Red Hill, Mundoora)
Barn Hill is a prominent hill about 8 km SW of Red Hill, about 6 km east of Mundoora and 160 km NNW of Adelaide. It is conspicuous from the plains around Port Broughton, and is named The Bluff on some maps. Stanwell Corporation, sold their interest in Barn Hill to Transfield Services Infrastructure in December 2007 and on 2009/06/18 AGL Energy Limited announced that it had acquired the rights to Barn Hill Wind Farm. Transfield held public meetings at Redhill and Mundoora to discuss development of the wind farm in June 2008; they submitted a Development Application to the Port Pirie and Wakefield councils in September 2008 and this was approved in late January 2009. The Barn Hill Wind Farm, if it is built rather than simply being sold from one potential developer to another, will fill the space along the Barunga Range between Clements Gap and Snowtown Wind Farms. (That is, from the Hope Gap Road in the south to the Torrs Gap Road in the north.) As of June 2010 my information is that AGL was awaiting the passage of the Renewable Energy Target amendments in the Federal Senate.
| |||||||||||||||||||||
|
Wind home Top SA wind farms Index |
|
| Status | No. of turbines | MW each | Total MW | Completed | Capacity factor | Lat | Long |
|---|---|---|---|---|---|---|---|
| Operating | 23 | 2 | 46 | Opened March 2005 | 29% | S 37.61° | E 140.29° |
|
The first two turbines were switched on in early November 2004. The wind farm consists of 23 turbines each of 2 MW. AGL has signed a deal to purchase all the power generated at this wind farm.
This wind farm was formerly called Lake Bonney Central Wind Farm.
Also see Canunda photos and notes on visiting Canunda.
| Further information on Canunda Wind Farm | |
|---|---|
| Wind generators | Vestas 2 MW |
| Rotation rate | Between 9 and 19rpm, depending on wind speed |
| Tower height | 67m |
| Blade length | 39m |
| Total height to blade tip | 107m |
| Cut-in wind speed | 4m/sec. |
| Max. energy wind speed | 14m/sec. |
| Cut-out wind speed | 25m/sec. |
| Distribution power line | 33kV double-circuit, 16 km long |
| Substation | Snuggery |
|
In 2009 Canunda wind farm generated 119 GWh of renewable electricity and fed it into the National Grid.
|
|
Pacific Hydro held meetings at Georgetown, Gulnare and Gladstone in late July 2008 for community information sessions. Planning Approval for construction has been received from the Northern Areas Council, but as of January 2010 is under appeal. Pac. Hydro have a web page at "https://www.pacifichydro.com.au/Default.aspx?tabid=250". A 'referral' giving more information on the proposal can be downloaded from the EPBC (Federal Department of the Environment, Water, Heritage and the Arts: Environment Protection and Biodiversity Conservation Act) site. (Search under Referrals and public notices.) I would like to thank Terry Teoh of Pacific Hydro for much of the above information.
NewsFrom ABC On-line news, 2009/04/06Pacific Hydro is waiting on planning approval from the Northern Areas Council, and the council is waiting on more information about the lighting on the wind farm from Pacific Hydro. Pacific Hydro spokesman, Andrew Richards, said that they are "hopeful of being able to pursue it [the wind farm project] fairly quickly some time next year" (2010). I had it from Emily Wood on 2011/07/04 that "Carodys Hill is continuing to progress, albeit slowly". |
|
Wind home Top SA wind farms Index |
|
| Status | No. of turbines | MW each | Total MW | Completed | Lat | Long |
|---|---|---|---|---|---|---|
| Operating | 33 | 2 | 66 | September 2005? | S 34.80 | E 135.56 |
| Cathedral Rocks Wind Farm is south of Port Lincoln in southern Eyre Peninsula. Port Lincoln is 250 km west of Adelaide as the crow flies, but considerably more by road. It is jointly owned by some combination of TRUenergy, Acciona and EHN (Oceania) Pty. Ltd. |
| Turbine make | Vestas |
|---|---|
| Tower height | 60m |
| Rotor diameter | 80m |
| Total area covered | 29 square kilometres |
| Annual production | 178 GWh |
| Capacity factor | 31% |
The annual production and capacity factor figures above are calculated from AEMO data for March 2009 to December 2011 data (inclusive) downloaded via the Australian Landscape Guardians '.csv' format download facility.
|
Not all of the turbines were running on 4th and 5th February 2006 in spite of there seeming to be ample wind.
|
|
Wind home Top SA wind farms Index |
|
The wind farm will consist of four turbine regions that will take advantage of the winds, predominantly from the SW and north, on both sides of the Peninsula. Seven years of collected data suggest that average wind speeds are better than eight metres per second. Under good visibility conditions the turbines will probably be just visible from the coast near Adelaide, at a distance of about 60 km, and more reliably from Mount Lofty. The wind farm will be about 70 km from the Adelaide CBD. The Wattle Point Wind Farm is just a little further from Adelaide. If built, this wind farm will be bigger than any currently in Australia, including the 420 MW Macarthur Wind Farm under construction in Victoria. The power will be sent to Adelaide by an undersea cable having a diameter of about 10 cm (because the existing power transmission lines are operating at their maximum capacity). High voltage direct current (HVDC) technology will be used. The lack of suitable transmission lines for the development of sustainable energy in Australia is discussed elswhere on this site. The project was initiated by local farmers and developers. The Ceres name comes from a ship that was powered both by sails and steam and built in 1876. Its captain, John Germein, bacame an early pioneer of Yorke Peninsula, and several of his decendents are among the farmers involved in the proposal. (Ceres is the name of the largest of the asteroids, and the first to be discovered, in 1801; and also the Roman goddess of agriculture.) A similar wind farm, with undersea transmission cable, could be built on Kangaroo Island, where the wind resource is probably even better than in this area. This may not have been proposed because of expected public resistance or because the undersea cable would have to be longer and therefore more expensive. |
| Status | # Turbines | MW each | Total MW | Construction date | Lat. | Long. |
|---|---|---|---|---|---|---|
| Proposed | Up to 176 | 3.4? | 600? | End of 2015 | S 34.61° | E 137.74° |
| Owner/operator | Suzlon |
|---|---|
| Project cost | Aus$1.3 billion |
| Capacity factor | More than 38% expected |
| Annual generation | About 2000 GWh/yr expected |
|
| Status | No. of turbines | MW each | Total MW | Completed | Lat | Long |
|---|---|---|---|---|---|---|
| Operating | 27 | 2.1 | 56.7 | Late 2009 | S 33.50° | E 138.11° |
|
For an interactive map and/or directions to Clements Gap go to ExplorOz.
While the turbines were imported, the towers were manufactured in Adelaide. Pacific Hydro has a Net page on the project, the full URL is "http://www.pacifichydro.com.au/en-us/our-projects/australia-/ clements-gap-wind-farm.aspx" (note that there should be no spaces in the URL).
| ||||||||||||||||||||||||||
Air seems insubstantial, but this can be misleading. It is interesting to note that at full production ten million tonnes of air will pass through the 27 turbines of Clements Gap Wind Farm each hour.
Estimated payback time for the "embodied energy" of the whole wind farm is approximately five months.
Most of the information for this section came from Pacific Hydro and Suzlon; in particular Terry Teoh of the former and Megan Wheatley of the latter.
I did a very short investigation on 2010/07/19.
The closest ocupied houses to the turbines of this wind farm seemed to be
at least one kilometre away.
|
Generation record for Clements GapThe graph on the right shows the power generation record for Clements Gap Wind Farm as recorded by AEMO (Australian Energy Market Operator) and downloaded via the ALG (Australian Landscape Guardians) Net site. The units are average megawatts generated month by month.Community fundingPacific Hydro established a Community Fund of $50 000 per year for the life of this wind farm; this is $1852 per turbine per year and, so far as I know, is more than most wind farms put into the local communities. The first year of operation of the fund was 2009 and as of September 2010 a total of $100k has been distributed.Air navigation lightsClements Gap Wind Farm had air navigation lights on a few of its turbines from construction at least to August 2010, but they were switched off by the end of the year.NoiseI have taken sound level readings at Clements Gap on two occasions (September and October 2010); both times I recorded a maximum of 54 or 54dB(A) at a distance of around 100m from a turbine. Both times the sound levels at distances of 300-500m were in the 40s, and at one or two kilometres, while the turbines were audible, my meter did not register a reading (it has a mimimum of 40dB).Also see notes on Visiting Clements Gap Wind Farm. |
|
Wind home Top SA wind farms Index |
|
Photo credit: Greg Farkas |
| Status | No. of Turbines | MW each | Total MW | Commissioned | Lat | Long |
|---|---|---|---|---|---|---|
| Operating | 1 | 0.15 | 0.15 | Around 1990 | S 29.03° | E 134.76° |
Coober Pedy is a remote town about 750 km NNW of Adelaide.
Its power supply is by expensive-to-run
local diesel powered generators, so even though
the area does not have a good wind resource this turbine was thought to be
worth building.
|
|
|
As of April 2011 it was proposed that the wind farm will occupy two areas on either side of the road through Hughs Gap, which is about 8 km north of Crystal Brook (see the map below). The southern section is approximately between the Crystal Brook to Hughs Gap road on the west, Heads Road on the east, and is just north of Bowman Park. The northern section will be on the hills to the west of Youngs Road (which runs along the top of the range and on which is the Heysen Trail) and bounded on the north by Collaby Hill Road.
The proximity of the proposed wind farm to the Heysen Trail will provide an oportunity for people to experience, first hand, the sounds and sites of wind turbines close at hand. There are few places in South Australia where the public can walk (or drive) close to a number of operating wind turbines. This must help educate the public and show that wind turbines do not present a health hazard.
Most of the land in this area has been cleared and grazed or cropped for many decades, but there are scattered patches of native scrub. I have been assured that very little scrub will be cleared for construction; wind farms are normally built around the scrub so far as possible.
The project was originally proposed by Wind Farm Developments who never took the project beyond the feasibility stage. Origin, who took the project over from WFD, have not yet (August 2010) provided a Net page about it.
On 2010/08/18 I was informed (pers. com. Elizabeth Weaver and other Origin employees) that in general the turbines will be sited a kilometre or more from houses not a part of the project. If the wind farm is built then Origin will set up a committee of local people to make the decisions about how their community grant money (no amount mentioned, but Origin give $25k/yr for Cullerin Range Wind Farm) will be spent.
Wind Farm Developments erected a 50m mast with anemometers about 2005 and
later stated that they confirmed the project as viable.
This tower was removed and Origin later built four more towers to
obtain information on the variation of the wind resource around the area.
By August 2010 Origin had eight months of data from their new anemometers
and this, combined with the Wind Farm Developments data, convinced them
that the resource was of sufficient quality for a viable wind farm.
| Status | No. of Turbines | MW each | Total MW | Construction date | Lat | Long |
|---|---|---|---|---|---|---|
| Proposed | About 40 | 2? | 80? | Undecided | Approx. S 33.29° | E 138.22° |
|
It seems unlikely that a development application will be submitted to the Pirie Regional Council (the only one now involved) before late 2011.
As a resident of Crystal Brook I look forward to the construction of this
wind farm with great anticipation.
The closest turbines will be around 4 km from my house.
|
Wind home Top SA wind farms Index |
|
|
A $4.5b project has been discussed by Tim O'Loughlin (SA Commissioner for Renewable Energy), representatives of Macquarie Capital, and SA Premier Mike Rann.
The project involves a 'Green Grid' (set of high capacity electricity transmission lines) for Eyre Peninsula and an interstate connector that would be built from Port Augusta via south-east SA to Heywood in Victoria. (This would also permit better use of the existing wind farms in the SE and development of more resources there.)
The existing power transmission lines on Eyre Peninsula (as shown on the map) are only 66kV and have no reserve capacity. It has been proposed that a high capacity transmission line be constructed to enable the development of four areas in particular:
|
Wind home Top SA wind farms Index |
Average wind speeds in these areas are anticipated to be greater than eight metres per second, a capacity factor of greater than 38% is expected to be achievable and 10 GW (10 000 MW) of wind power capacity could be installed (3000 to 5000 turbines of the size being built in 2010).
Similar power lines have been built at government expense for coal-fired power stations and mines in the past, but never for renewable energy in Australia. Power lines specifically for development of wind resources have been built in Texas.
The Leigh Creek coal reserves that supply the power stations at Port Augusta are expected to run out around 2017. The new wind power and interstate connector will go a long way to fill the gap in the national power supply when the Port Augusta power stations close down. (Also see Capacities of conventional power stations.)
The Port Augusta Transcontinental on-line news carried and article on the
proposal dated 2010/09/01.
|
|
REVE announced that Spanish company "Acciona has lodged plans to develop
a 144 MW wind power plant with Australia's government".
It is proposed to be about
15 km north of Naracoorte in southeast SA.
The REVE article went on to state that the development application could be submitted as early as the end of 2012. |
| Status | # Turbines | MW each | Total MW | Construction date | Lat. | Long. |
|---|---|---|---|---|---|---|
| Proposed | 48 | 3 | 144 | Unknown | S 36.83° | E 140.74° |
|
Wind home Index Top |
| There seems to have been little or no work on this project for several years (as of June 2009). |
| Status | No. of Turbines | MW each | Total MW | Construction date | Lat | Long |
|---|---|---|---|---|---|---|
| Approved | 18 | 3 | 54 | Undecided | S 38.05° | E 140.85° |
|
Wind Prospect have planning approval from the District Council of Grant
for this wind farm on the coast of south-eastern South Australia
between Port Macdonnell and Victorian border.
There seems little other information available. Wind Prospect had a page on Green Point, but have removed it. In late February 2009 54 Suzlon turbines became available to AGL (for use at Hallett). It seems that these were from a third party who had cancelled an order with Suzlon. Green Point seems to be the only Australian wind farm in the pipeline with 54 turbines planned. Of course this may be no more than coincidence, the cancelled order might not even have been Australian. |
|
Wind home Top SA wind farms Index |
Hallett wind farmsAs of February 2012 the Hallett group, if considered to be a unit, comprised the biggest wind farm in Australia (350.7 MW installed capacity). Second biggest is Lake Bonney (SA) at 278.5 MW, and third Waubra (Vic) at 192 MW. (All the power from the first four stages of the Hallett group goes to a single substation before being fed into the power transmission grid.)Not only is the Hallett group the biggest in installed capacity, it is by far the most productive wind farm in Australia, generating an average of about 116 MW. Once Bluff Range comes on line latter this year the Hallett wind farms will probably be generating an average of about 137 MW, almost twice as much power as Waubra (in second place) which is averaging about 69 MW.
A confusing feature of the Hallett area is that:
Not only are there many high capacity turbines at Hallett, but they are very productive; up to September 2010 both Brown Hill Range and Hallett Hill had achieved capacity factors of 40%, resulting in the Hallett wind farms generating more power than any other in Australia. 40% is exceptionally high for any wind farm and it is at least partly due to the very high quality of the wind resource in the area.
I believe that the closest occupied houses to the Hallett turbines are generally about one kilometre from the turbines.
The Hallett wind farms are a group of six, five of which were originally proposed by Wind Prospect; all are in the area around Hallett and Mount Bryan, north of Burra. The sixth, North Brown Hill Wind Farm, was added later. They are all around 170 km north of Adelaide. The originally proposed five developments aimed to have an output capacity of about 320 MW produced by 160 two-megawatt turbines.
Estimated costs of generation for the Hallett wind farms
Bluff Range Wind Farm
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Status | No. of Turbines | MW each | Total MW | Cap. Fac. | Completion | Lat | Long |
|---|---|---|---|---|---|---|---|
| Operating | 25 | 2.1 | 52.5 | 32% | Late 2011 | S 33.37° | E 138.80° |
| |||
| |||
|
Suzlon released a newsletter 2011/06/22. The last of the S88 turbines was almost in position and the overhead lines were competed. It was expected that the wind farm would be handed over to AGL some time in December. Cleanup and remediation, including grading disturbed areas, reseeding, and final drainage modifications were underway.
A prototype S97 turbine has been included in the project. Tim Knill – AGL, Manager Power Development – informed me (2011/06/31) that it was expected that the S97 "will produce about 15% more energy due to [its] larger rotor".
One of two types of concrete bases or turbine footings are commonly used for wind turbines. Gravity footings rely on a large and heavy mass of concrete to hold the turbine in place, while, if suitable bedrock is present a smaller mass of concrete can be bolted to the bedrock using rock anchors. Rock anchors were used on this project.
At least one prototype Suzlon S97 (97m diameter rotor) turbine is to be constructed at the far south end of the ridge. This turbine is expected to generate slightly more electricity at low wind speeds than the S88.
AGL have set up 2 web cams on site and hope to make the images available to the public. I saw on the webcam that the first turbine was completed by 2011/04/30 (photo on right).
| Total project cost | $120m expected |
|---|---|
| Turbine height | 80m |
| Max. blade tip height | 124m |
| Length of on-site access tracks | About 9 km |
| Greenhouse gas (CO2) abatement | 161 000t per year expected |
|
|
Wind home Top SA wind farms Index |
|
| Status | No. of turbines | MW each | Total MW | Commissioned | Capacity factor | Lat | Long |
|---|---|---|---|---|---|---|---|
| Operating | 45 | 2.1 | 94.5 | June 13th 2008 | 39% | S 33.36° | E 138.71° |
The capacity factor above was calculated from AEMO data (July 2009 to December 2011 inclusive) and is among the best I have calculated for Australian wind farms.
|
| The first Hallett turbine; from Bundaleer forest |
A company named Wind Prospect first proposed the farm and did initial work on assessing the wind resource and planning a possible layout.
| Cost of development | $5.4m |
|---|---|
| Cost of construction | $227.5m |
| Cost of first 2 years operations | $10.5m |
The turbines are Suzlon S-88 2.1 MW machines and the farm was constructed by Suzlon. The Suzlon parent company is based in Pune, India.
For an interactive map and/or directions to Brown Hill Range go to ExplorOz.
The cost of generating power at this wind farm are calculated on my Wind Power page.
Bendan Ryan (of Suzlon) informed me that they used Brett Lane and Associates of Melbourne for bird and bat monitoring. Lane et al apparently wrote the wind industry's 'best practice' recommendations for bird and bat monitoring.
I must express my thanks to Peter Reed and Brendan Ryan of Suzlon for their help in keeping me informed and showing me around this wind farm.
|
|
Wind home Top SA wind farms Index |
|
|
| Some of the Hallett Hill turbines with one of the few remnant sheoak (Allocasuarina stricta) trees in the foreground |
| Status | No. of turbines | MW each | Total MW | Capacity factor | Completed | Lat | Long | Cost |
|---|---|---|---|---|---|---|---|---|
| Operating | 34 | 2.1 | 71.4 | 39% | Late 2009 | S 33.55° | E 138.86° | $166m |
The capacity factor above was calculated from AEMO data (July 2009 to December 2011 inclusive) and is among the best I have calculated for Australian wind farms.
|
Hallett Hill Wind Farm is about 15 km South of Hallett and a very few kilometres west of the township of Mount Bryan. It is the only farm of the Hallett group owned by ANZ (through fully-owned subsidiaries Energy Infrastructure Trust and Infrastructure Capital Group Ltd).
ABC on-line news, 2008/08/29, reported that:
"Energy company AGL has sold its wind farm near Burra in the mid-north of South Australia in a deal it says is worth $59 million. Energy Infrastructure Trust will own the Hallett Hill Wind Farm and fund the rest of the project's construction. But AGL will operate and maintain the wind farm and buy all the electricity produced."
The wind farm was constructed by Suzlon using Suzlon S-88 V3 turbines. I believe the tube sections of the towers were manufactured in Adelaide.
"AGL Energy (AGL), operator of the Hallett Hill wind farm (Hallett 2) in mid-north South Australia near the township of Mt Bryan, has taken a range of steps to deal with a noise complaint at Hallett 2. During commissioning of Hallett 2, which consists of 34 x 2.1 MW wind turbines, extensive noise testing and monitoring was carried out by specialist noise consultants to determine compliance with noise guidelines. When a resident neighbouring the wind farm raised concerns about noise, AGL engaged a specialist noise consultant to assess noise conditions at the residence. During the second round of noise testing at the residence, preliminary results showed that some audible tones were detected under certain conditions. Upon becoming aware of the tonality issue in December 2010, AGL promptly shut down a number of wind turbines in proximity to the residence. Sixteen (16) of the 34 turbines are currently shut down at night. AGL has been working with the turbine supplier to rectify the defect and co-ordinate testing with the neighbouring resident. The supplier has developed a permanent acoustic treatment to address the tonality issue."On 2012/01/05 I received the following from Adam Mackett, AGL's man in charge of Hallett Hill Wind Farm:
"The sixteen wind turbines were shutdown in late October and progressively returned to full operation after the permanent acoustic treatment was installed at each turbine."
|
Note that the generation is well down in the last three months of 2011; this could be due to closing down the 16 turbines over-night. The calculated capacity factor up to the end of Sept. 2011 was 40.5%, while that for the last quarter of 2011 was down to 33.0%. However, Brown Hill Range shows a similar decling in generation in the last quarter of 2011, so I'd say the situation is unclear. The lack of clear and detailed information from AGL does not help at all.
| Cost of development | $3.0m |
| Cost of construction | $189.1m |
| Cost of first half year's operations | $3.1m |
| Hub height | 80m |
| Max. blade tip height | 124m |
| Swept area of each turbine | 0.6ha |
| No. truck journies during construction | 1240 |
| High tension cable for rock-anchor footings | 130 km |
| Rock trenching for 33kV reticualtion | 17 km |
| Concrete used | 3400m3 |
| Steel for towers | 5800 t |
| Underground cable | 17 km |
| Overhead cable | 10 km |
| Total weight of material transported to site | 10 350t |
|
Wind home Top SA Wind Farms Index |
Mount Bryan Wind FarmThe Environment, Resources and Development Court of SA brought down a judgement in the case of "Quinn and Ors v Regional Council of Goyder and Anor" on 2010/11/24. The development plan consent was granted subject to a number of conditions. Parts, at least, of the judgement make interesting reading. Since then it has been reported (Adelaide Now, 2011/01/29) that the ERD Court decision has been appealed to the Supreme Court.
|
|
Mount Bryan Wind Farm is to be built near Mount Bryan (the hill, not the township), about 5 km East of Hallett, and about 12 km NNE of Mount Bryan township (map).
There has been some concern over a remnant stand of Eucalyptus trees (Eucalyptus globulus bicostata) in this area (April 2008). It seems that this particular stand of trees could be up to 4000 years old. Sandra Kanck (then South Australian Democrat MLC) said that the stand of trees is only 20m from one of the proposed turbines. (I believe the site of this turbine has been moved because of these trees.) While this stand of E. globulus bicostata may be the only one known in South Australia, the species is common in the Otway Ranges in Victoria.
| |||
|
|
An email from Tim Knill of AGL Energy (12th March 2010) included the following on ecology: "there are some patches of native grass/shrubs but very few trees on the ridge tops. Any unavoidable clearance of native vegetation will require conservation set-aside areas to be established. We expect that all trees will be protected."
The Heysen Trail passes over Mount Bryan and on to Hallett (through the broader valley in the lower right of the aerial view). I walked this section of the Trail on 30th August 2010. The view on the upper right is fairly typical of the Mount Bryan range. There are more large gums in some of the lower areas, there are more shrubs on some of the hill-sides, there is more conspicuous damage from over-grazing in some areas (lower photo). I am informed by a reliable source (Millie Nicholls) that the shrubs, which are very common in the area, are Melicytus dentata, common name tree violet. These all appeared to be very heavily grazed. (I have other images of the Mount Bryan area if anyone needs them.)
Once built the wind farm will make this section of the Heysen Trail much more popular because it will present an oportunity for people to walk a dedicated walking trail close to, and among, a group of modern wind turbines. I cannot think of any comparable oportunity elsewhere. Providing this first hand experience – seeing and hearing wind turbines at close range – to many people must help educate the public on the facts of wind turbine sound levels and visual impact.
At various points along this section of the Heysen Trail there are views
of the Hallett Hill Wind Farm, some seven kilometres to the SW, and the
more distant Brown Hill Range wind farms to the NW.
| Expected CO2 abatement | 256 000 tonnes per year |
|---|---|
| Payback time for embodied energy | About six months |
| Average wind speed at hub height | About 9.0 metres per second |
| Expected capacity factor | 43% |
Mount Bryan wind farm is expected to be one of the most productive (in
proportion to its size) in Australia.
|
Wind home Top SA wind farms Index |
|
This wind farm is about 23 km from Hallett (map) and immediately north of the Brown Hill Range Wind Farm (Hallett #1). Wind Prospect has quite a detailed Net page about the project and you may find information about the project on AGL's site. First power into the grid was 2010/08/14. As of 2010/10/20 all turbines have been fully erected, one section has been handed over to AGL and other sections were going through reliability testing and commissioning. Power fed into the national grid was still increasing, but the best so far was more than 70 MW.
North Brown Hill will be one of the the biggest wind farm in SA and in Australia. Ward Civil won the contract for the footings of North Brown Hill and, I believe, made rock anchor bases that are smaller than previously used in the area. I believe they took around 50 cubic metres of concrete each and are 1.4m deep rather than the 2.3m deep bases Built Environs designed ones for earlier Hallett wind farms. AGL sold this wind farm to the Energy Infrastructure Investments consortium about October 2009. | ||||||||||||||||||||||||||||||
| ||||
|
|
| Status | No. of turbines | MW each | Total MW | Construction date | Lat | Long |
|---|---|---|---|---|---|---|
| Proposed | 37 | 2.1? | About 78? | Undecided | S 33.41° | E 138.84° |
|
International Power has proposed building this wind farm about 5 km West of
Hallett.
I gather they have created a subsidiary company called Willogoleche Power
to build this farm.
A post on ABC on-line news, 2011/07/14, stated that a proposed extension of from 26 turbines to 37 turbines was appoved by the Goyder Council. ABC News, 2011/12/08, reported that an appeal against the increased number of turbines by six Mid-North residents had been withdrawn after an out-of-court agreement between them and the developer.
Community fundingInternational Power also own Canunda Wind Farm, for which they provide a small community assistance fund. |
|
Wind home Top SA wind farms Index |
|
|
The electricity generated will go to a sub-station on site, then to the existing 275 kV power transmission line that runs through the area.
Contacts for inquiries: Email: enquiries@hornsdalewindfarm.com.au
Phone: 1800 015 398
Fax: 02 9293 2322
| Status | # Turbines | MW each | Total MW | Operation expected | Lat. | Long. |
|---|---|---|---|---|---|---|
| Proposed | 105 | 2 to 3? | Up to 315 | 2014 or 2015 | S 33.05° | E 138.54° |
| Owner/operator | Investec Bank (Aus) Ltd. |
|---|---|
| Project cost | Aus$900 million |
| Annual generation | 1050 GWh expected |
| CO2 abated | 1 250 000 tonnes per annum expected |
| Operating life | 25 years expected |
| Turbine type | Not yet decided (Sept. 2011) |
| Total height | 150 m, to blade tip (max.) |
|
Wind home Top SA wind farms Index |
|
|
Pacific
Hydro are proposing this wind farm near the township of Keyneton
which is about 65 km NE of Adelaide in the Mount Lofty Ranges.
At this early stage the company has consulted with the closest neighbours,
done some environmental assessments, developed a proposed layout and
apparently collected some wind data.
They hope to lodge a planning application later in 2011.
The wind farm will not have aviation lighting. Pacific Hydro say that "the site boundary is approximately three kilometres east of Keyneton and that it will connect to the grid via a transmission line that crosses the site. It is expected that the turbines will be at least 1.5 km from the nearest homes. Pacific Hydro have run at least two public information sessions. I've read that they hope to submit a Development Application by the end of this year (2011). I have independent information that there isn't much remnant vegetation that will be affected. The area has been grazed for 150 years and there isn't much left. The same source informed me that Pacific Hydro have done 'a particularly good job of consulting the community'. |
| Status | # Turbines | MW each | Total MW | Construction date | Lat. | Long. |
|---|---|---|---|---|---|---|
| Proposed | 42 | 2 to 3 | Up to 130 | Unknown | S 34.56° | E 139.09° |
Community fundingPacific Hydro are one of the more generous companies in regard to Community Funds. |
|
Wind home Index Top SA wind farms |
Lake Bonney wind farms
Lake Bonney Stage 1 wind farm
Lake Bonney Stage 2 wind farm
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Trust Power proposed this wind farm to be built south of Sellicks beach
and north of Myponga, near Mount Terrible and Mount Jeffcott,
on the Fleurieu Peninsula.
Trust Power's
Net site seems not to have been updated for a long time.
Shortly after it being reported that construction would start in early 2010 the South Australian Government announced that it has refused to vary major development approval of the wind farm (Trust Power wanted to build taller towers, 110m high). Subsequently Trust Power stated they would drop the project. This all happened in late August, early September 2009. In January 2011 SA Planning Minister Paul Holloway said that it is no longer appropriate to grant further extension of the development approval. |
|
Wind home Top SA wind farms Index |
|
| Status | No. of turbines | MW each | Total MW | Completed | Capacity factor | Lat | Long |
|---|---|---|---|---|---|---|---|
| Operating | 35 | 2 | 70 | December 2005 | 29% | S 33.63° | E 136.68° |
|
| One of the Mount Millar wind turbines near Cowell and Cleve, South Australia; at sunset |
This wind farm was previously called Yabmana. It is built along seven kilometres of hill-top roughly between Cowell and Cleve. (It is sign-posted from the Cowell-Cleve road.)
The Eyre Peninsula Tribune, on 14th March 2006, stated that construction of this wind farm started in late 2004 and was completed in December 2005. Power started being generated on February 28th 2006.
This is an interesting and scenic wind farm to
visit.
Most of the turbines are quite close to a public road along a ridge top with
good views over Spencer Gulf.
|
|
Some of the Mount Millar wind turbines; late afternoon You can see more photos of Mount Millar Wind Farm. |
| Project cost | Aust$130 million |
|---|---|
| Footings | |
| Footing type | Mass |
| Mass footing rely on their weight to hold the turbine
in place, rather than the alternative of bolting them to the bedrock. | |
| Footing diameter | 20m |
| Material in footings | 40 tonnes of steel and 800t of concrete. |
| Turbines | |
| Turbine type | Enercon E70 |
| Gearing | No gearbox, direct drive, see below |
| Tower height, to hub | 85m |
| Total height to blade tip | 120m |
|
Annular generatorThe Mount Millar Wind Farm is different to other SA wind farms in that the turbines do not have gear boxes; this, presumably, is why the nacelle of these turbines has a larger diameter than most. A quote from the manufacturer, Enercon..."The annular generator is of primary importance in the gearless system design of ENERCON wind turbines. Combined with the rotor hub it provides an almost frictionless flow of energy, while the gentle running of fewer moving components guarantees minimal material wear. Unlike conventional asynchronous generators, the ENERCON annular generator is subjected to minimal mechanical wear, which makes it ideal for particularly heavy demands and a long service life. |
|
Wind home Top SA wind farms Index |
|
| Status | No. of turbines | MW each | Total MW | Construction date | Lat | Long |
|---|---|---|---|---|---|---|
| Approved | ? | ? | 118 | Unknown | S 32.62° | E 137.57° |
|
As of September 2009 this project seems to be in the hands of
Infigen Energy who mentioned it in
a pdf file, 'Australian development pipeline' (no longer available).
This file gave the project status as "Initial DA [development application?]
received".
As of 2012/02/07 there seem to be no Net pages dedicated to this project and Infigen don't mention it on their Wind Energy Projects page. |
|
|
This proposed wind farm is interesting for it's large size and the fact that
the proposal came from a group of 30 farmers who recognised the potential on
their land.
Michael McCourt, of Beachport, is heading the project on behalf of the
farmers.
The agreement by Macquarie Capital Group Ltd. to take "responsibility for all of the ongoing development activities for the proposed wind farm" (Border Watch, 2009/12/22) is very significant because it indicates that financial backing has been obtained; always a hugely important mile-stone for any wind farm development.
The wind farm is to be built on the Woakwine Range between Beachport and Mount Benson. Beachport is 78 km NW of Mount Gambier, Mount Benson is about 60 km NNW of Beachport. I suspect that substantial upgrading of the power transmission system will be needed before the project can proceed. |
|
Wind home Top SA wind farms Index |
|
| Status | No. of turbines | MW each | Total MW | Completion due | Lat | Long |
|---|---|---|---|---|---|---|
| Proposed | 30 to 35 | 3? | 90 to 105? | Undecided | Approx. 33.99° | 139.10° |
|
Robertstown is 50 km ESE of Clare, 21 km north of Eudunda, and 110 km NNE of Adelaide; the wind farm is about 6 km west of the Robertstown township. The proponent is Tasmania-based Roaring 40s, who have a page on the project. They have announced that they hope to submit a development application in early 2010; their manager for this project is Michael Hogan.
It was earlier reported that this and Stony Gap Wind Farm were to be extensions of Waterloo Wind Farm, but in fact Roaring 40s are treating all three as separate projects.
In November 2009 Roaring 40s announced that they would be holding an information session about this project in Robertstown 'in the near future'.
|
Wind home Top SA wind farms Index |
|
|
This farm is west of Snowtown and about 150 km north of Adelaide.
For an interactive map and/or directions to Snowtown go to
ExplorOz.
A company named Wind Prospect originally planned up to 105 wind turbines each of 2 MW. There are 47 turbines in the Snowtown Wind Farm, more are planned for Snowtown Stage 2. |
| Status | No. of turbines | MW each | Total MW |
First power to grid | Completed | Capacity factor | Lat | Long |
|---|---|---|---|---|---|---|---|---|
| Operating | 48 | 2.1 | 100.8 | March 2008 | Early September 2008 | 41% | S 33.73° | E 138.11° |
| The capacity factor was calculated from AEMO data from July 2009 to December 2011 inclusive, is among the best I have calculated for Australian wind farms and among the best for on-shore wind farms anywhere in the world. |
|
|
2007/12/28 |
| Owner | Trust Power Ltd. |
|---|---|
| Operator | Suzlon |
| Project cost | Aust$220 million |
| Expected output | 350 GWh/yr |
| Greenhouse gas savings | 345 000t/yr |
| Turbine type | 47 Suzlon S88-2.1 MW 1 Suzlon S95-2.1 MW |
| Tower height (to hub) | 80m |
| Height to blade tip | 124m |
| Rotational speed | 15 to 17.6RPM |
| Rotor diameter | 88m |
| Speed at blade tip | 69 to 81m/sec. or 249 to 292 km/hr |
|
While TrustPower own this wind farm, the Indian based company Suzlon built it, operate it and maintain the turbines.
The contract calls for a minimum availability of 97%; that is, as I understand it, total turbine/hours of downtime must be no more than 3% of the total turbine/hours in a year.
The wind farm started feeding power into the grid in December 2007 and was officially opened on 2nd November 2008. In the Australian Electricity Generation Report of 2008, available from Australian Policy Online, this wind farm is listed as the eleventh largest renewable energy power station in mainland eastern Australia, and the fifth largest wind farm, by generation for 2008, generating 195 MWh.
Some of my photos of Snowtown Wind Farm are on another page.
|
|
|
Full URL for Snowtown Stage 2, "http://www.trustpower.co.nz/index.php?section=162" There are 48 turbines at Snowtown Stage 1 (August 2011). Trust Power's Net site (2011/08/11) speaks of "the remainder of the 130 approved turbines, with a proposal to add another 19 turbines". This suggests that up to another 101 turbines might be built. I received the following from Trust Power on 2011/01/23: "Graeme Purches (our Community Relations Manager) ... advises that we have all planning approvals and landowner agreements and are preparing financial justification for Board consideration. We hope to be able to proceed [with construction] this year." I emailed TrustPower (2008/07/30) requesting information on any proposed expansion of the Snowtown Wind Farm and received a reply from Clayton Delmarter. He said that they received approval for 130 turbines back in 2004, and I quote him... "So we can still install 83 turbines under the original approval – we are looking at various layout options, but essentially if you assume the same turbine type (nothing confirmed at this stage) there is around 174 MW of capacity left to build out.On 2011/09/15 Clayton informed me that construction was expected early next year. For email to Trust Power try clayton.delmarter@trustpower.co.nz or rodney.ahern@trustpower.co.nz. |
|
Wind home Top SA wind farms Index |
|
|
| Status | No. of turbines | MW each | Total MW | Commissioned | Capacity factor | Lat | Long |
|---|---|---|---|---|---|---|---|
| Operating | 23 | 1.5 | 34.5 | September 2003 | 27% | S 35.57° | E 138.16° |
|
It is located across two hills south of Rapid Bay, Starfish Hill and Salt Creek Hill, with 8 turbines on Starfish Hill and 15 on Salt Creek Hill. For an interactive map and/or directions to Starfish Hill go to ExplorOz.
| Project cost | Aust$65 million |
|---|---|
| Annual production | Approx. 100 GWh |
| Turbine make | Neg Micon (now Vestas) |
| Height to turbine hub | 68m |
| Height to blade tip | 100m |
| Rotor diameter | 64m |
An interesting feature of this wind farm is that the tips of the turbine blades can be rotated independently of the remainder of the blade. This can be used to stop the turbines when needed.
Also on this Net site: Starfish Hill photos, notes on visiting.
|
|
Wind home Top SA wind farms Index |
Some of the turbines made a strange sound when rotating slowly. After a time I concluded that the turbine blades must be hollow and partly filled with water which cascaded backward and forward as the turbines rotated. When they rotated at full speed the centrifugal force must have been sufficient to keep the water at the far end of the blades and stop the cascading. I have since been informed that it is unlikely that there could be water in the blades, but have heard no other explanation for the strange sound.
|
I am informed that the Neg Micon turbines did not have transformers in the
Nacelle, unlike Vestas models, so there would be fewer likely causes of
a fire.
|
|
Wind turbines at Starfish Hill, Cape Jervis, South Australia This was the first South Australian wind farm. |
|
Stony Gap Wind FarmStony Gap is about 28 km east of Clare, 13 km east of Farrell Flat, and 126 km NNE of Adelaide. A location map is in the notes on the Robertstown Wind Farm.TRUenergy has lodged a Development Application (DA) with the Regional Council of Goyder seeking to obtain Development Plan Consent for their proposed Stony Gap wind farm.
The project was started by Roaring 40s who held a community information session on this wind farm at the Burra Town hall on 2009/12/03. Since then, Roaring 40s was broken up and the Stony Gap WF project was taken over by TRUenergy, who have a Net site on the project. |
|
Wind home Top SA wind farms Index |
Vincent North Wind Farmalso known as Sheoak Flat Wind Farm
This project was proposed by Pacific Hydro and was to be at Sheoak Flat between Port Julia and Port Vincent on Yorke Peninsula. The company obtained planning permission for the wind farm. On May 19th 2010 several newspapers reported that Pacific Hydro had decided to allow planning consent to lapse.
Quoting from the Yorke Peninsula Country Times, 2008/04/15, "Currently the
132kv [power transmission] line serving Yorke Peninsula is at capacity
and, until the capacity constraints are resolved and the electricity
transmission infrastructure upgraded, this project and others like it are
likely to remain on hold."
Note that this same problem has stopped the development of Wattle Point
Stage 2 wind farm.
The SA Government talks big on sustainable energy, but does much less.
The information in this table came from Pacific Hydro. | |||||||||||||||||||||||||
|
Wind home Top SA wind farms Index |
|
|
|
|
Wind home Top SA wind farms Index |
Waterloo was constructed by Tasmania-based Roaring 40s, who have a Net page on the project, at a cost in excess of $300m. In April 2011 it was passed to TRUenergy. The wind farm will use Vestas Wind Systems V90-3.0 MW turbines. (The V90 is an abbreviation: V for Vestas and the 90 indicates a 90m diameter for the swept circle of the turbine blades.)
On 2010/08/19 Dijana Jevremov of Roaring 40s informed me that the closest turbine to a residence at Waterloo Wind Farm is "at or near to 2 km away".
| Status | No. of turbines | MW each | Total MW | Capacity factor | Completion due | Lat | Long |
|---|---|---|---|---|---|---|---|
| Operating | 37 | 3 | 111 | 30% | Late Oct. 2010? | Approx. 33.98° | 138.92° |
|
|
|
| Turbines | |
|---|---|
| Turbine type | Vestas V90 3 MW |
| Tower height | 80m |
| Blade length | 44m |
| Weight of each blade | 6.7t |
| Tower weight | 145t |
| Nacelle weight | 70t |
| Hub and nose cone weight | 22t |
| Foundations | |
| Concrete used | 360 cubic m each |
| Steel reo used | 30t each |
| Total weight | 910t each |
| Cables | |
| Buried aluminium | 28 km |
| Buried optical fibre | 28 km |
|
The turbines are along the top of a well defined sharp ridge running parallel to, and four kilometres west of, Tothill Range. The point specified by latitude and longitude in the table above is in the approximate centre of the wind farm and is about 3.5 km east of Waterloo. Waterloo is about 30 km SE of Clare.
An interesting point about this wind farm is that the turbines are 43% bigger than most of those previously constructed in northern South Australia; ie. 3 MW rather than 2.1 MW. (3 MW turbines have also been used at Lake Bonney Stage 3 Wind Farm.)
On the grape vine: The quartzite rock on the ridge is so hard that it has to be blasted before footings can be built. However, it is generally too fractured for rock anchors to be used, so the footings are of the heavy gravity type.
The viability of two other wind farms,
Robertstown and
Stony Gap, is also under investigation in
the same area.
|
|
Wind home Top SA wind farms Index |
A good night's sleep at WaterlooThere have been complaints about turbine noise and health concerns related to the Waterloo Wind Farm.I went to the Waterloo wind farm on the evening of 2012/02/10 and set up my swag beneath one of the turbines. The number of kangaroos on the ridge impressed me; I must have seen at least eight, including a small joey. I also saw a pair of wedge-tailed eagles circling near the turbines. All were aparently in good health. The wind varied from a moderate to a stiff breeze, so the turbines were operating all night. While I could plainly hear the turbines whenever I woke at night, I had no problem at all in getting a good night's sleep. Right at the foot of the turbine the sound of the turbine gear-box dominated the sound of the blades as they passed through the air. I noticed that when I moved away 100m or more all I could hear was the blades. When passing through Waterloo in the evening I stopped my car and listened for the turbines. I could not hear them. The breeze in the nearby trees was making a fair amount of sound. In the morning I again passed through Waterloo and stopped. There was still a stiff breeze on the ridge where the turbines were, but very little air movement in Waterloo. I thought I might just be able to hear the turbines, but could not be sure; birds were making far more noise than the turbines. |
|
|
The wind farm started operating in the first half of 2005.
Alinta sold this wind farm to a wholly-owned subsidiary of the ANZ, Energy Infrastructure Trust, in April 2007 for Aus$225m. It is run by AGL.
The Google-Earth image at the right shows the locations of individual turbines and a number of the access roads.
Wattle Point is unusual in being (as of late 2009 at least) the only large Australian wind farm laid out in a grid-pattern on level ground. It would be interesting to know how much wind-shadowing there is due to this lay-out.
In the Australian Electricity Generation Report of 2008, available from Australian Policy Online, this wind farm is listed as the eighth largest renewable energy power station in mainland eastern Australia, and the third largest wind farm, by generation for 2008, generating 248 MWh.
|
| Status | No. of turbines | MW each | Total MW | Completed | Capacity factor | Lat | Long |
|---|---|---|---|---|---|---|---|
| Operating | 55 | 1.65 | 91 | May 2005 | 33% | S 35.10° | E 137.72° |
|
| Type of turbine | Vestas V82 |
|---|---|
| Total area of wind farm | 11.5 square kilometres |
| Tower height | 67m |
| Blade length | 40m |
| Height to blade tip | 110m |
| Expected life | 25 years |
| Expected annual generation | 312 GWh |
|
312 GWh/annum was roughly 2% of South Australia's electricity at the
time Wattle Point was built.
The above data were from Research Institute for Sustainable Energy, (RISE). | |
Generation record for Wattle PointThe graph on the right shows the power generation record for Wattle Point Wind Farm as recorded by AEMO (Australian Energy Market Operator) and downloaded via the ALG (Australian Landscape Guardians) Net site. The units are average megawatts generated month by month.Air navigation lightsI noticed on a visit in late September 2010 that there were no lights on any of the turbines.Community fundingIt appears that there is no community fund associated with Wattle Point Wind Farm.NoiseIn September 2010 I took sound level readings among the turbines in a light breeze. The highest reading was 47dB(A) and I noted at the time that a car travelling at an estimated 60 km/hr 400m away was making more noise.More photos are at my Wattle Point photos page; also see my notes on Visiting Wattle Point Wind Farm. |
|
Wind home Top SA wind farms Index |
Wattle Point Stage 2 Wind FarmAlternatively known as Troubridge Point Wind FarmThis was proposed to be a 25 MW wind farm near the present Wattle Point farm. At least to October 2008 it has not been built. The hold up seems to be the lack of capacity in the transmission lines. Following an inquiry I sent to the District Council of Yorke Peninsula I received the following by email... Please be advised that Council have approved of a second wind farm near Wattle Point a couple of years ago, however, the development has not proceeded due to the fact that there is insufficient capacity in the transmission lines to accommodate additional power loadings.More recently (October 2008) I have had confirmation from another source (I will not give the name) that the reason this farm was not built was a lack of support by the State Government. So it seems yet again that a wind farm development that could happen is not going to happen because of lack of the needed government support, in this case, state government support. |
Woakwine Range Wind FarmThis project is proposed by Infigen Energy who own the nearby Lake Bonney Wind Farm.Infigen Investor Relations sent me links to two MP3 files, on 2010/12/15, of interviews with Frank Boland, Infigen Project Manager, who was speaking about the Woakwine Wind Farm. Together with the wind farm size data and probable construction date given in the summary table below, he said that the cost of the project was expected to be greater than $800m. He said that the northern section would comprise 49 turbines and go from Cape Jaffa to Mount Benson, the largest, southern, section would go from Mount Hope to Lake Bonney (98 turbines), and there would be another six turbines near Robe. He also said that the closest turbines to houses of people without a financial connection to the wind farm would be 600 to 700m away. Infigen seem to have little information about the project on their Net pages as of 2011/12/10.
Infigen has a pdf file on its 'Australian development pipeline' that mentions the project. The power transmission network in the region is already strugling to handle the load from the existing wind farms; it will need substantial development before this project can be brought online. |
|
Wind home Top SA wind farms Index |
World's End Wind Farm
The Burra Broadcaster published a front page article on 18th August, 2004 stating that a company named Wind Developments Australia Pty. Ltd. were planning to build an 80 to 90 turbine wind farm at World's End (about 15 km South of Burra); each turbine being 2 MW. The newspaper also stated that construction was expected to take about eight months and the Company hoped to start construction by the end of 2004. This seems to me one of the least likely of the Mid-North SA wind farms to be built. There is no evidence that I know of for any action at all on the project, and I have been told by someone in a position to know that the turbine sites are inappropriate for efficient operation. Allco Financial Services listed this as one of their projects. Allco, in severe financial difficulties, called in administrators in November 2008. |
|
Wind home Top SA wind farms Index |
|
|
In addition to those detailed above many others wind farms are proposed
(table below),
but I have been unable to find anything
about when, if ever, these are likely to be constructed.
Information concerning these would be appreciated, my email
address is at the top of this page.
If and when any of these proposed wind farms look likely to be built I will write them up in more detail. Until some significant money is spent on investigation a proposed wind farm may be little more than wishful thinking and is not worth covering in more detail than that below. |
| Region | Wind Farm | Proposer | MW | Status |
|---|---|---|---|---|
| Eyre Peninsula | Elliston Stage 1 (Tungketta Hill) | Ausker Energies & ANZ Infrastructure Services | 55 | Planning approved No transmission lines |
| Elliston Stage 2 | As above | 65 | Planning approved | |
| Lake Hamilton/Sheringa | Hydro Tasmania | 110 | Feasibility | |
| Mount Hill | Ratch Aust. Corp. | 80 | Feasitility | |
| Sheringa Beach | Ausker Energies | 100 | Feasibility | |
| Uley | Babcock and Brown and National Power | 160 | Feasibility | |
| Fleurieu Peninsula | Kemmis Hill | Origin | ? | |
| Waitpinga | Waitpinga Wind Farm P.L. | ? | Disallowed | |
| Lower North | Thompson Beach | Water and Energy Systems P.L. | ? | Prefeasibility |
| Mid North | Kulpara | Ratch Aust. Corp. | 80 | Prefeasibility |
| Skillogalee Wind Farm | DP Energy Australia PL | ? | Prefeasibility | |
| South East | Kongorong | Ratch Aust. Corp. | 30 to 120 | Prefeasibility |
| Mount Benson | Babcock and Brown National Power | 130 | Feasibility | |
| Lake George | Babcock and Brown National Power | 120 | Feasibility | |
| Unknown | Weymouth Hill | Meridian Energy
and Wind Farm Development | ? | |
|
Wind home Top SA wind farms Index |
|
As of November 2010 I have visited, or attempted to visit, 13 of the 14 operating South Australian wind farms. The best readily available map that shows all the minor roads is probably RAA's Clare Valley regional road map. Below are some notes on local accommodation, accessibility, photographing possibilities, etc. They are listed in alphabetical order. Lake Bonney has been listed with Canunda because these two, independently owned and operated, wind farms are contiguous and it is not easy to see where one finishes and the other starts. Similarly the AGL wind farms in the Hallett area have been grouped together.
All wind farm turbines in SA are on private land. While you can often get quite close to some turbines via public roads, there will be others that cannot be approached except by crossing private land. In my experience most farmers are very reasonable and will not object if you walk onto a property a short distance from a boundary fence, leave gates as you find them, are considerate of livestock, and do not go near sheds or homesteads without asking permission. I suggest not driving onto private land without permission. Most land-owners would prefer you to ask permission before entering on their land at all, but it is very often difficult to know who owns what land and where he/she lives. If you meet anyone, politely explain what you are doing.
I would appreciate information that would allow me to improve this section,
for example, further information on local accommodation options.
| |||||||||||||||||||||||||||||
|
Wind home Top SA wind farms Index |
| Connector | Owner/Manager | Capacity | Connection Points |
|---|---|---|---|
| Heywood | ElectraNet SA | 500 MW import 300 MW export | Lower SE SA to Portland Vic. |
| Murray-Link | transEnergie | 200 MW | Redcliff Vic. to Monash SA |
| Proposed SA-NSW Interconnector (SNI) 1 | NEMCO | ? | ? |
| Proposed SA-NSW Interconnector (SNI) 2 | Transgrid | ? | SA/NSW border to Robertstown via Monash |
|
At the date above there was a very destructive wind in the Port
Pirie/Crystal Brook/Red Hill area.
From the large number of trees blown down I
estimated that it was similar in strength to two previous very
damaging winds; one about 1980 and the other around 1999.
I wondered if there would be any likelihood of such a wind damaging
wind turbines.
Ken Jack of Stanwell (the proposers of Barn Hill Wind Farm, Red Hill – Wandearah area) kindly informed me of the wind velocities that he recorded. As some wind farm operators treat their wind velocity records as confidential, it would be unfair for me to publish the exact figure here. However, I can say that the strongest gust was well below the sort of wind that might be expected to bring down a wind turbine. |
IndexLinks to subjects on this page...
On this page... Allendale Wind Farm Annular generator Ardrossan Wind Farm Barn Hill Wind Farm Big blow of 3rd Jan 05 Bluff Range Wind Farm Brown Hill Range Wind Farm Canunda Wind Farm Capacities of conventional power stations Carmodys Hill Wind Farm Cathedral Rocks Wind Farm Ceres Project Clements Gap Wind Farm Collaby Hill Wind Farm Colour coding for wind farm status-Table Contents Coober Pedy Wind Farm Crystal Brook Wind Farm Electricity imports decreasing due to wind power-Graph Elliston Stage 1 Wind Farm Elliston Stage 2 Wind Farm Emissions from generation-Graph Eyre Peninsula wind project Exmoor Wind Farm Future of wind power Generation costs at Hallett Generation duration for SA wind-Graph Green Point Wind Farm Growth of the SA wind industry Gulnare Wind Farm Hallett-map Hallett #1 Hallett #2 Hallett #3 Hallett #4 Hallett #5 Hallett Hill Wind Farm Hallett wind farms Hornsdale Wind Farm Installed wind power, by wind farm-Table Installed wind power in SA Introduction Kemmis Hill Wind Farm Keyneton Wind Farm Kongorong Wind Farm Kulpara Wind Farm Lake Bonney Stage 1 Wind Farm Lake Bonney Stage 2 Wind Farm Lake Bonney Stage 3 Wind Farm Lake Bonney wind farms Lake George Wind Farm Lake Hamilton-Sheringa Wind Farm Lincoln Gap Wind Farm Mount Benson Wind Farm Mount Bryan Wind Farm Mount Hill Wind Farm Mount Millar Wind Farm Myponga-Sellicks Hill Wind Farm North Brown Hill Wind Farm Operating SA wind farms-Graph Other proposed wind farms Port Augusta Wind Farm Power interconnectors Robe Wind Farm Robertstown Wind Farm SA electricity consumption-Graph SA wind farm generation-Graph Sheoak Flat Wind Farm Sheringa Beach Wind Farm Skillogalee Wind Farm Snowtown Wind Farm Snowtown Wind Farm Stage 2 South Australian wind farms Starfish Hill Wind Farm Stony Gap Wind Farm Thompson Beach Wind Farm Top Troubridge Point Wind Farm Turbine shut-down Hallett-2 Uley Wind Farm Vincent North Wind Farm Visiting Canunda Wind Farm Visiting Cathedral Rocks Wind Farm Visiting Clements Gap Wind Farm Visiting Hallett wind farms Visiting Lake Bonney Wind Farm Visiting Mount Millar Wind Farm Visiting SA wind-farms Visiting Snowtown Wind Farm Visiting Starfish Hill Wind Farm Visiting Waterloo Wind Farm Visiting Wattle Point Wind Farm Waitpinga Wind Farm Waterloo Wind Farm Wattle Point Stage 2 Wind Farm Wattle Point Wind Farm Weymouth Hill Wind Farm Where SA and Mid-North SA stand on the world scene Willogoleche Hill Wind Farm Wind energy contribution to SA power Wind energy contribution to SA power-Graph Wind farm generation data Wind farms by location Wind farms by region Wind generation in SA by region-Graph Wind output at high demand periods-Graph Wind power in SA Woakwine Range Wind Farm Worlds End Wind Farm |
|
Home Wind home Top SA wind farms |
|
Home Wind home Top SA wind farms |